Utility, industrial and institutional work across Tanzania, from 33 kV substations to standby power and surveillance.
Featured case study
Turnkey installation, testing and commissioning of an 800 kVA ground-mounted substation and a 33 kV high-tension utility line to support expanded production.
Integrating a high-capacity substation without disrupting live facility lines. The site demanded careful structural work, precise route clearing, dielectric testing and close coordination with utility grid operators.
Certified line crews erected steel-reinforced pole structures and made the HV cable terminations. Our engineers ran thermographic, ratio and dielectric tests and calibrated the protection relays before energisation.
Energised smoothly with zero safety incidents and full TANESCO regulatory compliance.
A selection of completed and ongoing contracts.
Send us your site details and drawings. An engineer will review them and come back with a scope and quotation.